Ninth Line Widening

LINK TO PROJECT PAGE ON CITY WEBSITE

Check this page for regular updates on the progress of the Ninth Line widening project, including lane closures and other traffic and community impacts.

Please avoid travelling in the area if possible. Thank you for your patience as we take the necessary time to improve the road network, access and safety in our community.

This page last updated on August 5, 2026

Update: July 31, 2026

Please find below a summary of the construction progress completed by Pacific Paving Ltd. (PPL) and its subcontractors as of July 21, 2026, for the Ninth Line Widening Project.

Roadworks- Pacific Paving:

  • Pacific Paving Ltd. completed the installation of temporary traffic control for Phase 1, extending from Eglinton Avenue West to Janice Drive.
  • Beginning July 22, 2026, the contractor commenced the removal of existing catch basins and installation of new catch basins along the northbound lanes (NBL) of Ninth Line, (Eglinton Avenue West intersection) and stopped (Janice Drive intersection).
  • A total of 13 new catch basins has been installed, and all the existing catch basins within this section have been removed in accordance with the contract drawings.

 

  Culvert Rehab Works- Subcontractor Alliance Verdi Civil Inc. (AVC):

  • To facilitate culvert rehabilitation works, Ramudden was engaged by Pacific Paving Ltd. to install temporary traffic control for access to the northbound lanes at the culvert location. This work was completed on June 29, 2026.
  • Alliance Verdi Civil Inc. (AVC) completed site mobilization, including the delivery of equipment, materials, and personnel, in preparation for the culvert rehabilitation works.
  • Alliance Verdi Civil Inc. retained Triple A as the subcontractor for asphalt removal. On July 3, 2026, Triple A completed the removal of the asphalt surface and approximately 20 mm of the existing concrete deck from the culvert slab in preparation for rehabilitation.
  • Subsequently, Alliance Verdi Civil Inc. completed the following demolition works:
    • Removal of the east-side sidewalk of the culvert.
    • Removal of the east-side parapet railing of the culvert.
  • In addition, Verterra Shoring, the shoring subcontractor, completed the installation and concrete placement of all support piles required for the temporary protection system. These works provide support and ensure the safe maintenance of live traffic adjacent to the active construction area

 

Subcontractor EC Power-Installation of temp electrical poles:

  • Derry Road W: Four poles are installed out of eight: two at the northeast corner and two at the southeast corner are installed.
  • Doug Leavens Boulevard: Two poles have been delivered out of four. Two more poles are still required.
  • Osprey Boulevard: The northeast, southeast, and northwest poles have been installed but are not yet anchored. SW poles still need to be installed (some trees need to be cut st SW corner to facilitate the work)
  • Britannia Road: Seven poles have been installed and anchored. One southeast pole is still left to install.
  • Thomas Street: All poles have been installed and anchored. The spans and wires have also been installed and connected.
  • Henrietta Way: Four poles have been installed and anchored. One southwest anchor is still pending because of a conflict.
  • Burdette: Four poles have been installed and anchored. Eleven traffic signal heads and the pedestrian stands have been installed. The spans and wires have been connected and tested. The system only needs to be turned on. The existing streetlight arms and lights will be transferred to the temporary poles when the traffic signals are switched over to the temporary system.
  • Erin Centre Boulevard: Two poles have been installed and anchored at the northeast and southeast corners. Two poles are still left to install.
  • Eglinton Avenue: All eight poles have been installed. The wires, traffic signal heads, and pedestrian stands have been installed, connected, and tested. The streetlight arms are installed, but the lights are still pending. The existing lights will be transferred when traffic is switched to the temporary signals.

GEMS Environmental Sampling

  • A total of 67 soil samples were collected for assessment from Derry Road west to Eglington Avenue.

PPL-Removing Topsoil

  • PPL removed the topsoil from the west side of Ninth Line moving from south towards north, approximately between 200m north of Eglinton Ave to Arvona Place.

 

Update: June 11, 2026

I was pleased to be joined by officials from the Ontario Ministry of Infrastructure, MPP Sheref Sabawy, City of Mississauga staff and project partners for the Ninth Line Widening groundbreaking on Monday, June 8.

News Release: Construction begins on Ninth Line improvements – June 8, 2026

 

Update: November 7, 2025

The major capital construction project to widen Ninth Line from Eglinton Avenue to Derry Road begins.

Early Work

Construction Contract

  • Tender – November 2025
  • Award – January 2026
  • Schedule – to be determined, anticipated to begin Spring 2026 at Eglinton Avenue and conclude late 2027 at Derry Road

 

The detailed design for the new roadway configuration largely follows the environmental assessment approved in 2021 and will include two travel lanes in each direction separated by raised medians or centre left turn lanes. A protected cycle track and distinct sidewalk will be constructed on both sides of the newly widened road. New traffic signals are planned for Skyview Street/Mahoney Gate, Tacc Drive, McDowell Drive and Beacham Street. Once complete, a new Miway transit route is expected to service the length of Ninth Line.

Work will begin in the south near Eglinton Avenue and progress northerly to Derry Road. It is a major capital project expected to take at least 18 months. There will be dust and noise, road and lane closures, and other traffic impacts and these will be communicated in advance of the related work as much as possible. In general, residents and commuters are encouraged to plan for delays and/or consider alternate routes where possible. Thank you for your patience and understanding.

The City is grateful to the Ontario government who has provided $10 million in grant funding for this project.