Community Meeting: Save the Date

I have confirmed the date and venue for the next community meeting on the Flood mitigation measures in the Lisgar District. Please save the date and plan to attend. Wednesday, October 18, 2017 – 7 pm Our Lady of Mount Carmel Catholic Secondary School, 3700...

Flooding Update from Staff: Aug. 25

Current Activities The draft report related to the storm sewer leakage testing in the Golden Locust Drive area has been reviewed by staff and comments have been provided to AmecFW. Flushing of the FDC system is on-going and is expected to be complete by next week with...

Flooding Update from Staff: Aug. 18

Current Activities The draft report related to the storm sewer leakage testing in the Golden Locust Drive area has been received and is currently being reviewed by staff; Flushing of the FDC system is on-going and is approximately 50% complete. Operations staff noted...

Flooding Update from Staff: Aug. 10

Current Activities The leakage testing of the Phase 1 storm sewer lining (in the Golden Locust Drive area) has been completed and AmecFW has advised that we will receive the testing report early next week. The draft memo summarizing the monitoring results of the July...