by Sue McFadden | Jul 17, 2017 | Lisgar Flooding
I sent the following e-mail on behalf of City of Mississauga staff on Friday afternoon, related to the flooding experienced in the Black Walnut area from the night before. There were two homes in Ward 9 that reported flooding, in addition to the 14 on Black Walnut...
by Sue McFadden | Jul 8, 2017 | Lisgar Flooding
This email is intended to provide an update on the Lisgar Implementation project, which is currently focused on storm sewer lining work and dewatering of the utility trench. Storm Sewer Lining The Request for Tender for the Phase 2 storm sewer lining work was released...
by Sue McFadden | Apr 17, 2017 | Lisgar Flooding
I received the following update from staff on the ongoing work in the Lisgar District. Storm Sewer Lining (Phase 1) Pipeflo Contracting completed the sewer lining works for the Phase 1 area on March 17. A piece of every liner that was installed was sent for testing...
by Sue McFadden | Jan 16, 2017 | Lisgar Flooding
In early January 2017, as a result of significant rain and snow melt, I posed some questions to Commissioner Geoff Wright (of Transporation and Works) regarding ongoing monitoring of the storm water system in Lisgar. My questions are in bold, his responses follow:...
by Sue McFadden | Oct 31, 2016 | Lisgar Flooding
Updates from Dec. 15, 2011 to Oct. 31, 2016. Storm sewer lining begins I am providing the City’s latest update on the current Lisgar Implementation project which includes lining select storm sewers and dewatering of the utility trench. Storm Sewer Lining...